Stress-test a delay claim against the project record
For: Contracts manager or claims consultant preparing or defending an extension of time claim
The pain today
The record of a delay is spread over site diaries, information requests, instructions, meeting minutes and letters. A claim built from the favourable part of that record fails when the other side produces the rest.
The ask
“I attached our draft delay claim, the contract notice provisions, and the site diaries, information requests, instructions, minutes and correspondence for the period. For each delay event, build the chronology that supports us, then attack it the way the other side would. Tell me which events stand, which notices were late, and what evidence is missing.”
Plain words, as you would say it to a colleague. Edit it to fit your case before you send it.
What you attach or connect
- Draft claim narrative with delay events
- Contract conditions on notice and time
- Site diaries and meeting minutes
- Information requests, instructions and change orders
- Project correspondence
The unit of work
One worker task per one delay event with its dated records.
Why a swarm fits
Each delay event draws on its own thin slice of a very large record. Events are independent, and an opposed team per event finds the adverse documents a drafter tends to skip.
Not for
Critical path or delay analysis on the programme, or valuing the claim. It tests the documentary record, not the schedule logic.
The decision tree
6 typed decisions, each with an action for every answer
At fixed moments in a run, the engine puts one narrow question to a decision model. The decision model never writes text: it answers yes or no with a probability, picks from listed options, or gives a score, about a small slice of the material. The engine then does exactly what this tree says, which is what makes the run auditable. The thresholds are the template's design values, not measured results.
Planner, while planning
Scope checkYes or no, with a probability
Before work starts on a unit
Is this record dated within the period of the delay event and does it mention the work area, drawing or instruction the event concerns?
Sees only: One record's date and subject line with the event's description
Why: Gives each event a thin, relevant slice of a very large project record.
- Yes: 0.60 or higherthenAccept
- Unsure: 0.30 up to 0.60thenEscalate to a strong model
- No: below 0.30thenSkip this unit
After workers, the judge checks
Evidence checkYes or no, with a probability
After a worker answers
Does the quoted record carry the date and author that the chronology entry gives it?
Sees only: One chronology entry and the header of the record it cites
Why: Every line of the chronology must survive a check against the document it relies on.
- Yes: 0.85 or higherthenAccept
- Unsure: 0.50 up to 0.85thenEscalate to a strong model
- No: below 0.50thenReject and retry
Evidence checkA choice among options
After a worker answers
Does the quoted notice letter's date fall within the period the quoted contract clause allows after the event date in the chronology?
Sees only: The notice clause, the notice letter's date line and the event date
Why: Late notice is the first point the other side will take, so it is tested from dates on paper.
- Within the periodthenAccept
- After the periodthenMark unresolved
- No notice found in the recordthenMark unresolved
- Clause period depends on awarenessthenAsk a person
Evidence checkYes or no, with a probability
After a worker answers
Does the quoted record attribute the same delay to a cause within our own control, such as labour, plant or late submittals?
Sees only: One delay event and one record offered by the challengers
Why: The challengers' adverse documents are held to the same quoting standard as the supporting ones.
- Yes: 0.85 or higherthenAccept
- Unsure: 0.50 up to 0.85thenEscalate to a strong model
- No: below 0.50thenReject and retry
Run control, between rounds
Another round?Yes or no, with a probability
Between rounds
Did the latest challenge round produce no adverse record that was not already listed for this event?
Sees only: The adverse record list before and after the round
Why: Stops searching the record for an event once the challenge has run dry.
- Yes: 0.70 or higherthenStop
- Unsure: 0.40 up to 0.70thenContinue
- No: below 0.40thenContinue
Accountable person, before anything is settled
Person decidesYes or no, with a probability
Before anything is reported as settled
Does the finding weaken an event, show a late or missing notice, or surface a record adverse to the claim?
Sees only: One event's verdict with supporting and adverse quotes
Why: The contracts manager and counsel decide what is claimed, conceded and disclosed.
Accountable: The contracts manager and legal counsel own what is claimed, what is conceded and what is disclosed.
- Yes: 0.40 or higherthenAsk a person
- Unsure: 0.15 up to 0.40thenAsk a person
- No: below 0.15thenAccept
The fleet: who does what
Model tiers by role, not brands: you choose the models. Strong reasoning models plan and reconcile, small fast models do the wide work, and the judge is a decision model from a different family, so it does not share the workers' blind spots.
Planner
A strong reasoning model splits the claim into events and indexes the record by date, author and subject.
Decisions here:1. Scope check
Workers
Small fast workers from an open-weight family build the dated chronology for one event with quoted records.
Designed for 10 to 250 agents, one worker task per one delay event with its dated records. Each worker receives only its own unit.
Judge, from a different model family
Challengers and a decision model from a different family search the same record for contradicting entries and late notices.
Decisions here:2. Evidence check3. Evidence check4. Evidence check
Reconciler
A strong reasoning model reports per event what survives, what is contested and which records cut against the claim.
Decisions here:5. Another round?
Accountable person
The contracts manager and legal counsel own what is claimed, what is conceded and what is disclosed.
Decisions here:6. Person decides
Checked before anything is accepted
- Every chronology entry cites a dated document
- Notice timing is checked against the quoted contract clause
- Adverse records are reported with the same prominence as supporting ones
What comes back
- Chronology per delay event with sources
- Events that survive challenge and events that do not
- Late or missing notices with the clause relied on
- Evidence gaps to close before submission
What to measure
- Challenges the claims consultant accepts as real weaknesses
- Adverse documents first found by the swarm
- Hours per delay event reviewed
- Cost per event
Names of measures only. No result is claimed for this template.
Templates open in the workspace chat with the ask filled in. Nothing runs until you send it.
Get early accessSign in to useMore in Real estate and construction
Abstract a lease portfolio with amendments and conflicts shown
For: Asset manager, lease administrator or acquisitions analyst handling a property portfolio
Each lease comes with amendments, side letters and notices.
Find conflicts between specifications, schedules and drawing notes
For: Design manager or lead consultant coordinating disciplines before tender or construction issue
Architectural, structural and services documents are written by different teams.
Level subcontractor bids against the scope, by specialist brief
For: Commercial manager, quantity surveyor or estimator comparing trade package bids
Bids for the same package arrive in different formats with different exclusions, qualifications and programme assumptions.